6.3 Module A4 – Transport to the site.
6.3 Module A4 – Transport to the site.
Written on .
6.3 Module A4 – Transport to the site.
Written on .
6.3 Module A4 – Transport to the site.
Written on .
| Aspect |
A-04 Transport of products to the construction site – screening and simplified LCA |
|||||
| Description |
This aspect is related to the transport of building products from the manufacturer’s production plant (or from regional storage) to the construction site. In practice, the assessment of transportation impact depends on the number of manufacturers or the number of regional storage providing a given building product. Such detailed information may be impossible to obtain without close cooperation with the building industry.Should the transport of products to construction site be included? What could the transportation distance be for each building product? Should losses be allowed for? | |||||
|
Related study objective |
☒ stand-alone LCA | ☒ comparative assertion | ||||
|
Related study phase |
☒ | ☐ | ☐ | ☐ | ☐ | |
| goal and scope definition | inventory analysis (LCI) | impact assessment (LCIA) | interpretation | reporting | ||
|
Relevant for |
||||||
| new buildings | existing buildings | building products | screening LCA | simplified LCA | complete LCA | |
| Provisions |
For screening and simplified LCA, transport to the construction site is optional, because of both potentially missing data and minor relevance at the scale of full building LCAs.If data are available, transport of products to the construction site may be included in a screening or simplified LCA unless they fall under the cut-off rules. The practitioner should use average transport distances and load factors. Rules should follow the recommendations of EN 15804. This includes the impacts of the transport and the impacts of any transport-related losses of material and its disposal (i.e. the impact of manufacturing material that is wasted as a result of transport, and the impact of disposing of the waste). Losses should be documented, where they occur. | |||||
| Rules from: |
EN 15978: 7.4.3.2 Boundary of the Transport to and from site (Module A4) EN 15804: |
|||||
| Guidance |
Modelling of the life cycle stage ‘Transport to the site’ should be iterative, and linked to corresponding cut-off rules defined e.g. in EN 15804/EN 15978.
1) Specific guidance for building LCA studies 2) Specific guidance for product LCA studies Other studies, e.g. from the UK, have estimated that carbon emissions from freight transport of building products represent at least 5% of the embodied carbon from manufacture. For building LCA (accounting for replacement of building products during the use stage and the end of life), it does not represent more than 5% of the non-renewable primary energy, owing to the higher share of the use phase in building LCAs, based on a French case study [Lasvaux 2010]. |
|||||
Written on .
Written on .
6.4 Module A5 – Construction installation process
Written on .
| Aspect |
A-06 Construction installation process impacts for screening LCA |
|||||
| Description |
Construction site impacts are driven mainly by the groundworks (fuel consumption), the transport of products, water and energy consumption (e.g. electricity), and the capital goods (such as crane, bungalow etc.), but also by the transport of construction workers. Under specific goal and scope, it might be interesting for a construction company or a building designer to assess the impacts of Module A5 by means of a default approach, without looking in detail at the different aspects, such as land preparation, water, energy and capital goods. | |||||
|
Related study objective |
☒ stand-alone LCA | ☒ comparative assertion | ||||
|
Related study phase |
☒ | ☐ | ☐ | ☐ | ☐ | |
| goal and scope definition | inventory analysis (LCI) | impact assessment (LCIA) | interpretation | reporting | ||
|
Relevant for |
||||||
| new buildings | existing buildings | building products | screening LCA | simplified LCA | complete LCA | |
| Provisions |
The assessment of construction site impacts may be taken into account in screening LCA by means of a default approach using global default values for Module A5. The intended use of this methodology is to get an overview of the share of impact of Module A5 when considering the full building LCA. If the results are sensitive to Module A5, the practitioner should refer to a more detailed assessment. | |||||
| Rules from: |
EN 15978: 7.4.3 Boundaries of the construction process stage 8.5 Scenarios for the construction process stage (Modules A4–A5) |
|||||
| Guidance |
During the design of a building, it may be difficult to assess the information for land preparation, water and energy consumption, owing to the lack of data. However, information on the quantities of building products are information available upstream of a building project from the construction companies. One possibility is then to assess the construction site impacts from the building product impacts, for which the level of detail is comparatively higher. Such a rough estimation may be sufficient for some screening LCA studies of buildings. It is not necessary to define default values at the level of each impact source for Module A5, which considerably reduces the level of complexity in the first step of a building LCA study.The link between this information needs default values to be provided based on statistical studies for each building type or construction system. Figure 14 represents a theoretical example, for one environmental indicator and for one building type and construction system, of the share of impact between the building products and the four aspects of the construction site taken as examples in this guidance (energy, water, transport of workers, and capital goods).
Figure 16: Breakdown of impacts for a given indicator for one building type
The calculation steps required to derive the example results in Figure 14 might be as follows: 1) Calculate the impacts related to the building products (Iproduct). 2) Determine a ratio (default value) Ri, expressed as a percentage, for each aspect i of the construction site (energy, water, transport of freight, and capital goods). These default values can be derived from statistical studies of meter readings of representative construction sites, as well as for the building product impacts. It is then possible to assess the impact of aspect i of the construction site by means of the global impact of the building products and the ratio (default value): Ii = Iproducts × Ri. Such a methodology may be followed by the LCA practitioner, and adapted according to the goal and scope of the study. To obtain representative ratios (default values), the LCA practitioner or LCA tool developer would need to work closely with or contact the construction companies to make such default values available. |
|||||
Written on .
| Aspect | A-07 Land preparation and earthwork during the construction process – screening and simplified LCA | |||||
| Description |
This aspect relates to the impact of site preparation, including the fuel consumption of, for example skid-steer loaders or bulldozers during the groundworks and landscaping. Under the specific goal and scope, this aspect might be interesting for, say, a construction company that needs to identify the hotspots of its construction site. Should the land preparation and earthwork during the construction process be considered in the context of a screening or simplified LCA? | |||||
|
Related study objective |
☒ stand-alone LCA | ☒ comparative assertion | ||||
|
Related study phase |
☒ | ☐ | ☐ | ☐ | ☐ | |
| goal and scope definition | inventory analysis (LCI) | impact assessment (LCIA) | interpretation | reporting | ||
|
relevant for |
||||||
| new buildings | existing buildings | building products | screening LCA | simplified LCA | complete LCA | |
| Provisions |
The land preparation and earthwork may be included in screening and simplified LCA if they are relevant to the goal and scope of the study (e.g. a construction company might have more interest than a building designer in this aspect). | |||||
| Rules from: |
EN 15978: 7.4.3 Boundaries of the construction process stage 8.5 Scenarios for the construction process stage (Modules A4–A5)According to the rules from EN 15978, the system boundary for the construction process shall include the groundworks and landscaping |
|||||
| Guidance |
The practitioner should use default values (e.g. ratios or generic data) for screening and simplified LCA, and also refer to cut-off rules. Ratios can be defined with stakeholders. This aspect can be neglected for most construction projects, as it is of minor relevance. | |||||
Back to 4.4. Module A5
Written on .
| Aspect | A-08 Land preparation and earthwork during the construction process – complete LCA | |||||
| Description |
This aspect relates to the impact of site preparation, including the fuel consumption of, for example skid-steer loaders or bulldozers during the groundworks and landscaping. Under the specific goal and scope, this aspect might be interesting for, say, a construction company that needs to identify the hotspots of its construction site. Should the land preparation and earthwork during the construction process be considered in the context of a complete LCA? | |||||
|
Related study objective |
☒ stand-alone LCA | ☒ comparative assertion | ||||
|
Related study phase |
☒ | ☐ | ☐ | ☐ | ☐ | |
| goal and scope definition | inventory analysis (LCI) | impact assessment (LCIA) | interpretation | reporting | ||
|
Relevant for |
||||||
| new buildings | existing buildings | building products | screening LCA | simplified LCA | complete LCA | |
| Provisions |
The land preparation and earthwork should be included in complete LCA if they are relevant for the goal and scope of the study (e.g. a construction company might have more interest than a building designer in this aspect). | |||||
| Rules from: |
EN 15978: 7.4.3 Boundaries of the construction process stage
8.5 Scenarios for the construction process stage (Modules A4–A5) According to the rules from EN 15978, the system boundary for the construction process shall include the groundworks and landscaping |
|||||
| Guidance |
The practitioner should use detailed calculation (based on specific data) for complete LCA. The impact of land preparation and earthwork can be assessed using generic data accounting for the impact of the fuel consumption of construction machinery (e.g. skid-steer loaders or bulldozers).This aspect can be neglected for most construction projects, as it is of minor relevance. | |||||
Written on .
| Aspect | A- 09 Product storage on site before installation – screening and simplified LCA | |||||
| Description |
Storage of products on arrival at site before installation includes such aspects as maintaining specific temperature or humidity in a storage space on site, and protection from weather, vandalism, theft, etc. Under the specific goal and scope this aspect might be interesting for, say, a construction company that needs to identify the hotspots of its construction site. Should the storage of products be considered in the context of a screening or simplified LCA? | |||||
|
Related study objective |
☒ stand-alone LCA | ☒ comparative assertion | ||||
|
Related study phase |
☒ | ☐ | ☐ | ☐ | ☐ | |
| goal and scope definition | inventory analysis (LCI) | impact assessment (LCIA) | interpretation | reporting | ||
|
Relevant for |
||||||
| new buildings | existing buildings | building products | screening LCA | simplified LCA | complete LCA | |
| Provisions |
Product storage on site before installation may be included in screening and simplified LCA if it is relevant for the goal and scope of the study (e.g. a construction company might have more interest than a building designer in this aspect).If there are impacts from product storage (e.g. maintaining specific temperature or humidity conditions in a storage space on site) then this may be included in Module A5 next to the infrastructures required for the product storage (e.g. protection from weather, vandalism, theft), but these can be evaluated for significance using the cut-off rules.Any wastage because of poor product storage should be accounted for in Module A5 (manufacture, transport and disposal of wasted material). | |||||
| Rules from: |
EN 15978: 8.5 Scenarios for the construction process stage (Modules A4–A5) | |||||
| Guidance |
The practitioner should use default values (ratios) for simplified LCA. Such data can be defined with stakeholders. This aspect can be neglected for most construction projects, as it is of minor relevance. | |||||
Written on .
| Aspect | A- 10 Product storage on site before installation – complete LCA | |||||
| Description |
Storage of products on arrival at site before installation includes such aspects as maintaining specific temperature or humidity in a storage space on site, and protection from weather, vandalism, theft, etc. Under the specific goal and scope this aspect might be interesting for, say, a construction company that needs to identify the hotspots of its construction site. Should the storage of products be considered in the context of a complete LCA? | |||||
|
Related study objective |
☒ stand-alone LCA | ☒ comparative assertion | ||||
|
Related study phase |
☒ | ☐ | ☐ | ☐ | ☐ | |
| goal and scope definition | inventory analysis (LCI) | impact assessment (LCIA) | interpretation | reporting | ||
|
Relevant for |
||||||
| new buildings | existing buildings | building products | screening LCA | simplified LCA | complete LCA | |
| Provisions |
Product storage on site before installation should be included in complete LCA if it is relevant for the goal and scope of the study (e.g. a construction company might have more interest than a building designer on this aspect).If there are impacts from product storage (e.g. maintaining specific temperature or humidity conditions in a storage space on site) then this may be included in Module A5 next to the infrastructures required for the product storage (e.g. protection from weather, vandalism, theft), but these can be evaluated for significance using the cut-off rules.Any wastage because of poor product storage should be accounted for in Module A5 (manufacture, transport and disposal of wasted material). | |||||
| Rules from: |
EN 15978: 8.5 Scenarios for the construction process stage (Modules A4-A5) | |||||
| Guidance |
The practitioner should use detailed calculation based on LCI data for complete LCA. For most construction projects, this aspect is likely to fall under cut-off rules. | |||||