The frequency of replacement is related to the reference study period and the reference service life of the component to be replaced. The ratio between them could lead to a partial number of replacements (e.g. where the reference study period is 30 years but the reference service life for a component is 20 years). Should replacement cycles be calculated as ‘whole-number/full number’ of replacements, or does it make sense to calculate ‘proportionate/partial’ cycles of replacement?
Related
study objective
☒ stand-alone LCA ☒ comparative assertion
Related
study phase
☒
goal and scope definition
☐
inventory analysis (LCI)
☐
impact assessment (LCIA)
☐
interpretation
☐
reporting
Relevant for
new buildings

existing buildings

construction products

screening LCA

simplified LCA

complete LCA

Provisions
As the baseline scenario, replacement cycles have to be calculated in whole numbers, according to EN 15978 and EN 15804 (examples are given there). Only whole numbers of replacements are allowed (no partial replacements). The number of replacements is related to the reference study period and the reference service life of the component to replace. The number of replacements must be rounded up unless justified. In order to show the effect of improved durability, a scenario with partial replacement cycles can be made. This scenario has to be documented and justified, and a sensitivity analysis conducted by comparison with the baseline scenario.

Rules from
EN 15978 8.6.4 Scenarios for refurbishment – Module B5

9.3.3 Replaceable components and number of replacements

EN 15804 6.3.4.4.2 B1–B5 Use stage information modules related to the building fabric: – B4 Replacement
ILCD 6.10.3 Considered alternatives, the functional unit, and assumptions

Provisions: 6.10 Comparisons between systems


Guidance
Partial replacement numbers should be avoided. Replacement numbers should be rounded up, unless justified as described below:
The last replacement of components may be skipped, provided:
– the component is not essential to security, health or comfort;
– the absence of replacement is based on actual practice;
– the final replacement occurs during the last 10% of the study period;
– a specific maintenance scenario is developed in this case.